CFBISD provides Bond updates

During the December Board Meeting, Carrollton-Farmers Branch ISD Trustees were provided with a comprehensive construction update on ongoing Bond construction. Watch the full presentation HERE

These projects are organized into three categories: renovation work, replacement campuses, and crucial safety and security enhancements.

Project activity timeline:
  • Summer 2025: Construction was active across 19 CFBISD campuses
  • Current status: Construction is ongoing at 6 campuses
  • Summer 2026: The district plans to have work underway at 20 campuses
Overview of completed and ongoing renovation projects:
 
Creekview High School
  • Project type: Limited renovation
  • Progress: 50% complete
  • Completion date: August 2026
 
Kent Elementary School
  • Project type: Limited renovation
  • Progress: 50% complete
  • Completion date: August 2026
 
Rosemeade Elementary School
  • Project type: Limited renovation
  • Progress: 50% complete
  • Completion date: August 2026
 
Blalack Middle School
  • Project type: Major renovation
  • Progress: 20% complete
  • Completion date: August 2027
 
Davis Elementary School
  • Project type: Limited renovation
  • Progress: Substantially complete
  • Completion date: August 2025
 
Thompson Elementary School
  • Project type: Limited renovation
  • Progress: Substantially complete
  • Completion date: August 2025
 
Turner High School
  • Project type: Major renovation
  • Progress: 19% complete
  • Completion date: January 2027
 
Blanton Elementary
  • Project type: Limited renovation
  • Progress: Substantially complete
  • Completion date: August 2025
 
Smith High School
  • Project type: Significant renovation
  • Progress: Site mobilization
  • Completion date: Winter 2027
 
Polk Middle School
  • Project type: Minor renovation
  • Progress: 20% complete
  • Completion date: August 2026
 
Country Place Elementary
  • Project type: Minor renovation
  • Progress: 27% complete
  • Completion date: August 2026
 
Child Development Academy
  • Project type: Minor renovation
  • Progress: Substantially complete
  • Completion date: August 2025
 
Riverchase Elementary
  • Project type: Limited renovation
  • Progress: Substantially complete
  • Completion date: August 2025
 
Bush Middle School
  • Project type: Limited renovation
  • Progress: Substantially complete
  • Completion date: August 2025
 
Freeman Elementary
  • Project type: Limited renovation
  • Progress: Substantially complete
  • Completion date: August 2025
 
Landry Elementary
  • Project type: Limited renovation
  • Progress: Substantially complete
  • Completion date: August 2025
 
Ranchview High School
  • Project type: Limited renovation
  • Progress: Substantially complete
  • Completion Date: August 2025
 
Blair Elementary School
  • Project type: Limited renovation
  • Progress: Substantially complete
  • Completion date: August 2025
 
Field Middle School 
  • Project type: Critical maintenance
  • Progress: Substantially complete
  • Completion date: August 2025
 
McLaughlin Strickland Elementary 
  • Project type: Limited renovation
  • Progress: Substantially complete
  • Completion date: August 2025
 
Stark Elementary 
  • Project type: Limited renovation
  • Progress: Substantially complete
  • Completion date: August 2025
 
Carrollton Elementary
  • Project type: Replacement
  • Progress: Site mobilization
  • Completion date: August 2027
 
Bond fiber project
Trustees also learned that the Bond fiber project is nearly complete, expanding the district’s network and technology capabilities. 
 
Stay informed
CFBISD will continue to provide regular bond updates through ParentSquare, the district’s Bond website and social media.