CFBISD provides Bond updates
During the December Board Meeting, Carrollton-Farmers Branch ISD Trustees were provided with a comprehensive construction update on ongoing Bond construction. Watch the full presentation HERE
These projects are organized into three categories: renovation work, replacement campuses, and crucial safety and security enhancements.
Project activity timeline:
-
Summer 2025: Construction was active across 19 CFBISD campuses
-
Current status: Construction is ongoing at 6 campuses
-
Summer 2026: The district plans to have work underway at 20 campuses
Overview of completed and ongoing renovation projects:
Creekview High School
-
Project type: Limited renovation
-
Progress: 50% complete
-
Completion date: August 2026

Kent Elementary School
-
Project type: Limited renovation
-
Progress: 50% complete
-
Completion date: August 2026

Rosemeade Elementary School
-
Project type: Limited renovation
-
Progress: 50% complete
-
Completion date: August 2026

Blalack Middle School
-
Project type: Major renovation
-
Progress: 20% complete
-
Completion date: August 2027

Davis Elementary School
-
Project type: Limited renovation
-
Progress: Substantially complete
-
Completion date: August 2025

Thompson Elementary School
-
Project type: Limited renovation
-
Progress: Substantially complete
-
Completion date: August 2025

Turner High School
-
Project type: Major renovation
-
Progress: 19% complete
-
Completion date: January 2027

Blanton Elementary
-
Project type: Limited renovation
-
Progress: Substantially complete
-
Completion date: August 2025

Smith High School
-
Project type: Significant renovation
-
Progress: Site mobilization
-
Completion date: Winter 2027

Polk Middle School
-
Project type: Minor renovation
-
Progress: 20% complete
-
Completion date: August 2026

Country Place Elementary
-
Project type: Minor renovation
-
Progress: 27% complete
-
Completion date: August 2026

Child Development Academy
-
Project type: Minor renovation
-
Progress: Substantially complete
-
Completion date: August 2025

Riverchase Elementary
-
Project type: Limited renovation
-
Progress: Substantially complete
-
Completion date: August 2025

Bush Middle School
-
Project type: Limited renovation
-
Progress: Substantially complete
-
Completion date: August 2025

Freeman Elementary
-
Project type: Limited renovation
-
Progress: Substantially complete
-
Completion date: August 2025

Landry Elementary
-
Project type: Limited renovation
-
Progress: Substantially complete
-
Completion date: August 2025

Ranchview High School
-
Project type: Limited renovation
-
Progress: Substantially complete
-
Completion Date: August 2025

Blair Elementary School
-
Project type: Limited renovation
-
Progress: Substantially complete
-
Completion date: August 2025

Field Middle School
-
Project type: Critical maintenance
-
Progress: Substantially complete
-
Completion date: August 2025

McLaughlin Strickland Elementary
-
Project type: Limited renovation
-
Progress: Substantially complete
-
Completion date: August 2025

Stark Elementary
-
Project type: Limited renovation
-
Progress: Substantially complete
-
Completion date: August 2025

Carrollton Elementary
-
Project type: Replacement
-
Progress: Site mobilization
-
Completion date: August 2027

Bond fiber project
Trustees also learned that the Bond fiber project is nearly complete, expanding the district’s network and technology capabilities.